Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
<p>Write. up a change request and see if you can get it approved</p> <p> </p> <p>Make the change. It’s going to save time and nobody will want the project to take longer than it should.</p> <p> </p> <p>Figure out the impact on the scope of the work and the cost before you write up the change request.</p> <p> </p> <p>Tell the team member that you’ve already communicated the deadline for the project, so you can’t make any changes now.</p>
Figure out the impact on the scope of the work and the cost before you write up the change request.
Because any change to any project objective must be studied related to other objectives (Cost, Scope, ..etc)
Hello dear,
Thank you for the invite, the right answer is: Figure out the impact on the scope of the work and the cost before you write up the change request.
But it is important to realise that cutting the time down is not the main purpose, we should check the impact o the other2 constraints.
Regards,
Third option is the right one due to Project triple constraints concept.
Yes the third answer is the most apprpriate one. A project manager must analyze the influence/effect on other project constraints such as (risk, cost, quality etc) & then write for a change request.
For me i do beleive that the right answer is
((Figure out the impact on the scope of the work and the
cost before you write up the change request))
and i do agree with all professionals here choosed the third option
See the side effect and measure the cost/benefit result.
Figure out the impact before taking any decisión is the wrigth answer
vacationnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn