What routine procedure do you follow generally after completing the maintenance work?

user-image
Question ajoutée par ahmed shahin , electrical engineer , احدي ورش وزارة الدفاع
Date de publication: 2014/10/09
Mohamed Elbably
par Mohamed Elbably , Senior M3/EAM Business Consultant , INFOR

-Ensure work place is clean, all tools and test equipment are withdrawn.

-Visually check the nearby piping, tubes, valves and other equipment in the area, inform the control room & foreman about any abnormalities.

-Ensure that the work permit is signed off, that maintenance supervisors are informed about all observations, that test results are recorded on the appropriate check sheets and that maintenance history is recorded on the work history section of the work order for input in eAM/CMMS.

Leonardo Banzali
par Leonardo Banzali , Electrical Maintenance-trainer , Sadara Chemical Company

Do housekeeping and clear the area against hazards. Do necessary test run/commissioning to confirm stability of system and then turn-over to operations by closing the work permit.

LABIB KOOLI
par LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

A maintenance intervention is closed only if the necessary recording  task is done sometimes both on paper & soft support  

Utilisateur supprimé
par Utilisateur supprimé

reporting