What is the difference between Retained Logic, Progress Override and Actual Dates in Schedule Options, when you make Schedule in Primavera P6 ?

user-image
Question ajoutée par Ahmad Eltayeb , Planning Managment Department , Alexandria Construction Company
Date de publication: 2014/10/27
Mohammed Abdul Hannan
par Mohammed Abdul Hannan , Planning Manager , North 25 (Subsidary of Dubai Holding & Meraas)

Retained Logic: It retains the logic, means it follow the same logic the way schedule is linked and it cant go out of sequence

Progress Override: its used when activities are going out of sequence and they no more respect the sequence