What is the methodology you use to track project progress vs. plan from both a work completed and a financial standpoint?

user-image
Question ajoutée par Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company
Date de publication: 2014/12/08
Basit Ali
par Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

Things that are important:

  • Easy to understand
  • Easy to see exactly where in the project cycle we are
  • Can be replicated in an Excel spreadsheet
  • Lists tasks and sub-tasks
  • Shows roughly when a task occurs and how long it takes (accuracy of a week is fine, say Week36 for2 weeks)
  • Shows who is working/worked on the task
  • Can scroll down through100's of tasks/sub-tasks
  • Can easily hide large chunks of time where nothing is being worked on
  • Bonus: Can somehow display Completed, In Progress, Upcoming etc

 