Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
it depends on the failure ........if the concrete is bleeding and segregated ...then NO it must not be allowed ...but if the concrete carries lower than the specified slump , admixtures on site can be added .................plastic slump varies much now a days as3rd generation SP,s are used ...so you have to read alot about it ....hope my answer is helpful a little .....Thanks