<p>a) Create a contingency plan</p> <p>b) Create a risk management plan</p> <p>c) Create a WBS </p> <p>d) Create a scope statement</p>
c) Create a WBS
The correct answer is (C) Create a WBS.
The Correct I would for it is C. " Create a Work Breakdown Structure"
option c is the correct
Yeah that is the Work Breakdown Structure
WBS allows to break a project into manageable units by all team members, each level of the WBS for deepening the details of the tasks to final level: the concrete tasks to perform .
answer (C) Create a WBS.
Option: c) Create a WBS
BY Creating WBS statement
My answer will be c) Create a WBS
WBS
C : Create a WBS (work break down structure).