What are the actions the contractor perform at the site before excavation proceeds ?

user-image
Question ajoutée par Nasser Khan , manager , Godrej Group
Date de publication: 2013/07/03
naser abdalla
par naser abdalla , Site civil operations manager , Consolidated contractors for energy development

the area should be surveyed and slope stakes should be identified.
the contractor id responsible for identifying any and all underground utilities and secure them before the excavation starts.
safety tool box meeting should be conducted.