Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

How can i calculate the manpower of a factory?

user-image
Question ajoutée par Hosam Mohamed Abd Elhameed Farghaly Helal , Technical Sales Engineer , Gulf Gasket Factory
Date de publication: 2014/12/24
ched oliverio
par ched oliverio , Accountant , Freelance

First identify your plant capacity,counter it against your production requirement,

such that if plant capacity > production req take production requirement else take capacity.

Then identify all activities related to your plants operation,set the standard efficiency for each operation. Identify how many hours would you wish the plant to operate and follow this simple formula 

 

Plant Capacity or Production Req / (Operating Hours x Efficiency) = Manpower Requirement ;)

More Questions Like This