<p><strong>A. Used in the planning phase to do " what if for the project. </strong></p> <p><strong>B. Assist in the controlling of changes to the project. </strong></p> <p><strong>C. Is used in the process of preparing a WBS for the project. </strong></p> <p><strong>D. To measure future consequences of activities. </strong></p> <p><strong>E. a and d.</strong></p>
A PERT chart is a graph that represents all of the tasks necessary to a project's completion, and the order in which they must be completed along with the corresponding time requirements.
It is used in the planning phase to show possible scenarios with possible consequences.
Reference: http://www.pmpnotes.com/pmp-practice-tests/pmp-practice-questions-1/
The correct answer is :
E. a and d.
E: is my answer.
Agree with option E........................
Option "E".
Answer: E