Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Earned value is:

A. Actual cost of work performed.B. Completed work value.C. Budgeted cost of work performed.D. Percent complete.E. All except A.

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/19
Irina Chepel
par Irina Chepel , Personal trainer , Freelancer

I think it's C

Wolf Klaas Kinsbergen
par Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

 

Earned Value is an approach where you monitor the project plan, actual work, and work-completed value to see if a project is on track. Earned Value shows how much of the budget and time should have been spent, with regard to the amount of work done so far. so answer C

 

Ahmed Mohamed Ayesh Sarkhi
par Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

              ....... I Go With E Option :)

 

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

Current performance is the best indicator of future performance, and therefore using trend data, it is possible to forecast cost or schedule overruns at an early stage in a project. The most comprehensive trend analysis technique is the Earned Value method.

In a nutshell, Earned Value is an approach where you monitor the project plan, actual work, and work-completed value to see if a project is on track. Earned Value shows how much of the budget and time should have been spent, with regard to the amount of work done so far.

Here are five other definitions:

  1. Englert and Associates, Inc define it as, "A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned."
  2. Project Magazine defines it as, "A methodology used to measure and communicate the real physical progress of a project taking into account the work complete, the time taken and the costs incurred to complete that work."
  3. The user guide for Microsoft Project2003 defines Earned Value as, "A method for measuring project performance. It indicates how much of the budget should have been spent, in view of the amount of work done so far and the baseline cost for the task, assignment, or resources."
  4. Field Operative defines it as, "The physical work accomplished plus the authorised budget for this work. The sum of the approved cost estimates, (which may include overhead allocation), for activities, (or portions of activities), completed during a given period, usually project-to-date."
  5. NASA defines it as, "An integrated management control system for assessing, understanding and quantifying what a contractor or field activity is achieving with program dollars. EVM provides project management with objective, accurate and timely data for effective decision making."

Divyesh Patel
par Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

I will go for option E

souha safir
par souha safir , إدارية , قطاع التربية

c

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

E. All except A.

Sidrah Nadeem
par Sidrah Nadeem , Global Marketing Manager , Hill & Knowlton

From an accounting point of view its C!

Utilisateur supprimé
par Utilisateur supprimé

Earned value is:

 

 

C. Budgeted cost of work performed.

Utilisateur supprimé
par Utilisateur supprimé

C

racha hamed
par racha hamed , Front Desk Receptionist , Kurban Travel Services

i think it is choice B