In the first six month update on a 1 year, $100,000 project, the analysis shows that the BCWS is $50,000; the BCWP is $40,000 and the ACWP is $30,000.

What can be determined from these figures? 

 

A. The project is behind schedule and over cost.B. The project is ahead of schedule and under cost.C. The project is ahead of schedule and over cost.D. The project is behind schedule and under cost.

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/19
Mohamed Galal Hussein Ahmed Mohamed
par Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

CostPerformanceIndexCPI= CWP/ACWP=40000/30000=1.33>1

Then the answer is D

 

 

 

 

 

 

 

 

 

 

 

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

Wolf Klaas Kinsbergen
par Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

For me answer A

RAJ DAHIYA
par RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

_______________________________________________________________

D. The project is behind schedule and under cost.

_______________________________________________________________

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes, the correct answer is

D. The project is behind schedule and under cost.

 

CPI = EV/ AC = 40000/30000  = 1.333  > 1  ===> Below budget.  GOOD

SPI = EV/ PV = 40000/50000  =  .8  < 1   ===> Behind schedule.  NOT GOOD

 

              

Irina Chepel
par Irina Chepel , Personal trainer , Freelancer

It's not exactly my field of the expertise

Utilisateur supprimé
par Utilisateur supprimé

Agreed With Mr. Alex  

Muhammad samran
par Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

the answer is D

Divyesh Patel
par Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

I will go with answers given by experts.

hachem hadjira hachem hadjira
par hachem hadjira hachem hadjira , مسؤولة مصلحة بالكلية لحاملي الشهادات ورئيس,التعليم التقييم ،سيرت مكتب شؤون إجتماعية.مكلفة بالمخابر , جامعة العقيد أحمد دراية ولاية أدرار

D. The project is behind schedule and under cost

but i dont now a comtability 

and thinks for your invitation