Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Cost control is concerned with:

A. Allocating the overall estimates to individual work packages in order to establish a cost baseline. B. Influencing the factors which create changes to the cost baseline to ensure that changes are beneficial. C. Determining that the cost baseline has changed. D. A and BE. C and B

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/20
Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Most accurate answer is

E. C and B

Wolf Klaas Kinsbergen
par Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Cost Control is control chnages to the Project Budget, so answer B and C

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

Agree with Alex.

Ali Waqas Bhatti
par Ali Waqas Bhatti , Electrical Engineer , Lakson Group of Companies

Dear Alex ... Its the Option (E)

Irina Chepel
par Irina Chepel , Personal trainer , Freelancer

E C B I think

RAJ DAHIYA
par RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Option E i.e. Both C and B

Kaamila Tahseen
par Kaamila Tahseen , Change Management Team Manager , cognizant technology solutions

Answer is B as this falls in Control costs process. A is dealt in Estimate costs process C is handled in Determine buget process

Muhammad samran
par Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

E

Snezana Brankovic
par Snezana Brankovic , • Senior Consultant in Marketing Department , „Stankom” Business System

B,C,E optons.

Mohamed Batran
par Mohamed Batran , PROJECTS MANAGER , MBA, PMP , Alrajhi Ekhwan Group Co.

E. C and B

Mohamed Hamdy Kamal Riad
par Mohamed Hamdy Kamal Riad , Senior Solution Architect , IBM

D. A and B

More Questions Like This