Cost control is concerned with:

A. Allocating the overall estimates to individual work packages in order to establish a cost baseline. B. Influencing the factors which create changes to the cost baseline to ensure that changes are beneficial. C. Determining that the cost baseline has changed. D. A and BE. C and B

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/20
Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Most accurate answer is

E. C and B

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Cost Control is control chnages to the Project Budget, so answer B and C

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

Agree with Alex.

Ali Waqas Bhatti
by Ali Waqas Bhatti , Electrical Engineer , Lakson Group of Companies

Dear Alex ... Its the Option (E)

Irina Chepel
by Irina Chepel , Personal trainer , Freelancer

E C B I think

RAJ DAHIYA
by RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Option E i.e. Both C and B

Kaamila Tahseen
by Kaamila Tahseen , Change Management Team Manager , cognizant technology solutions

Answer is B as this falls in Control costs process. A is dealt in Estimate costs process C is handled in Determine buget process

Muhammad samran
by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

E

Snezana Brankovic
by Snezana Brankovic , • Senior Consultant in Marketing Department , „Stankom” Business System

B,C,E optons.

Mohamed Batran
by Mohamed Batran , General Manager , Al Blagha Group (ABG)

E. C and B

Mohamed Hamdy Kamal Riad
by Mohamed Hamdy Kamal Riad , Senior Solution Architect , IBM

D. A and B