Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Is there program make single PM with meter and calender base? if not how to handle PM need both Meter base 500H or Calender base 1 month ?

 

if you have PM for motor1 month  or500H which come first you will have to cancel the other or make reschedule for it but is there another way to handle this and is there a program doing this ? 

user-image
Question ajoutée par Ayman Baghdady , Planning & Maintenance Engineer , EMC company
Date de publication: 2015/02/04
احمد محمود احمد  سالمان
par احمد محمود احمد سالمان , CERTIFIED HEAVY EQUIP. MECHANICAL ENGINEER , MANTRAC EGYPT - CAT

Thank you for directing the question , in fact E.R.B . systems are used for a variety  of  activities out of which I use it for both planned production and maintenance although it is a bit complicated in programming.

Mohamed kaleem pasha
par Mohamed kaleem pasha , Production Manager , Gold Leaf Tobacco

It can also be done if we are tracking the output once certain output has been generated it should automatically trigger that PM is due.

More Questions Like This