A pull system that manufactures finished goods for inventory on the basis of demand forecasts is referred to as:

A) Economic order quantity. B) Just-in-time purchasing. C) Materials requirements planning (MRP). D) Relevant total cots.

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2015/02/07
VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
par VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Answer option (C)   >>>>>>>>>>>   Materials requirements planning (MRP)

Ahmer Zamir
par Ahmer Zamir , Consultant , Saleem Associates & Co

A) The Economic Order Quantity is the correct option 

Economic Order Quantity calculation is used to forecast  that economic quantity of material which is required to ordered keeping in view that unit cost , ordering cost , carrying/holding cost , stock run-out cost of material,required units of material keeping in view the forecast of demand of products.