Binil Paul , Sr. Planning Engineer , KEO International Consultants
First you need to have a baseline plan which you create at the initial level
Then make a copy of that and update the latter version using physical update percentage complete
Now go to assign baseline and maintain baseline and in the updated program assign the initial plan (theoretically updated by update progress) as the primary baseline
Now go to format columns and show the column BL physical percent compete and physical percent complete
Now in the columns vie u can see both planned and actual
Nw customise the name of columns as per your requirements
Good day.