I. Measurement of performance.II. Comparison of actual and standard.III. Analysis of causes of deviation.IV. Actual performance.V. Corrective action plan.
(a) (III), (IV), (V), (I), (II) (b) (II), (III), (IV), (V), (I)(c) (I), (II), (IV), (III), (V) (d) (IV), (I), (II), (III), (V)(e) (V), (IV), (III), (II), (I).
Option- D
IV). Actual performance
I). Measurement of performance
II). Comparison of actual and standard.
III). Analysis of causes of deviation
V). Corrective action plan
That would be the answer under D
its41235, answer is D.................
Good question, thank you.
(d) >>>>>>>>>>>>>(IV), (I), (II), (III), (V)
IV. Actual performance
I. Measurement of performance
II. Comparison of actual and standard.
III. Analysis of causes of deviation
V. Corrective action plan
I fully agree with you MR Vinod jetley.
thanks.
(d) (IV), (I), (II), (III),
(d) (IV), (I), (II), (III), (V)
(d) (IV), (I), (II), (III), (V) ............. . . . .
With my colleagues answers
Option D