Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Simply like: issues, safety, cost...............
In project weightage factors for electrical is
1.Electrical Equipment Installation-(Transportation to Site,Fix Base Frame, Aligning and Grouting ,Cable Connection, Testing.)2.Electrical Cabling-(Transportation to Site,Tray Erection,Cable Laying,Cable Connection,Testing.)
3.Electrical Fittings-(Installation,Cable Connection,Testing.)
4.Control panel-(Transportation to Site,Welding and Installation,Aligning and Grouting,Mounting Instruments,Cabling,Testing.)
5.Instrumentation-(Field Instruments-Support Erection,Mounting,Cabling,Loop Checking.)
6.Insulation-(Surface Preparation,Lagging,Cladding.)