Define of schedule performance index

if you planned to finish80% of construction in6 months time, but  you actually managed to finish only60% work due to delays ,than what is the SPI in that case??

 

user-image
Question ajoutée par kevil Vavaiya , Civil Engineer , ASCO Consulting Engineers
Date de publication: 2015/02/25
Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Schedule Performance Index (SPI) A measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV). SPI = EV divided by PV.

SPI = 60% /80%  =  .75  < 1  behind schedule.

Mohamed Galal Hussein Ahmed Mohamed
par Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

I agree with Mr.Alex as he gives the right answer.

 