What is Back Scheduling in MRP?

Select one:a. Production scheduling for the previous periodb. Analyzing the Lead times of materials and working backwards to raise the PO earlier to ensure timely delivery of materialsc. Taking back up of Scheduling Datad. All the above

user-image
Question ajoutée par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG
Date de publication: 2015/03/01
Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer is option b.Analyzing the Lead times of materials and working backwards to raise the PO earlier to ensure timely delivery of materials