An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed.

The project manager then issues a change request.What should the change request authorize?

A. Additional resources using the contingency fundB. Escalation approval to use contingency fundingC. Team overtime to meet scheduleD. Corrective action based on causes

user-image
Question ajoutée par Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.
Date de publication: 2015/03/27
Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The case didn't talk about going above budget or behind schedule so far, I would agree with

D. Corrective action based on causes

Adeniyi Aderemi
par Adeniyi Aderemi , IT infrastructure team lead , Jetlink Limited

Corrective actions based on causes.

Utilisateur supprimé
par Utilisateur supprimé

 

 

  I choose option D. Corrective action based on causes

 

 

 

Elke Woofter
par Elke Woofter , Project Assistant , American Technical Associates

I also go with option D) corrective action based on cause......

George Karaparambil
par George Karaparambil , Manager, Financial Analysis , Kerala Ayurveda Ltd, KATRA GROUP

Additional resources using the contingency fund

Muhammad Sajjad Anwar
par Muhammad Sajjad Anwar , Manager MIS , FAUJI FOUNDATION

D is the solution to meet the accepted deadline.

Rabbson Chikuse
par Rabbson Chikuse , Driver , Not working

Option D is a priority because if you take corrective action based on causes the request can be of a great importance because at first you will identify the causes and came up with a solution.