From the point of risking what is the difference between a lumpsum,unit price,target cost and cost plus contract of both the owner and the contractor?

user-image
Question ajoutée par ahmed shehab , site engineer , DHA Consulting & Engineering Design
Date de publication: 2015/03/27
Utilisateur supprimé
par Utilisateur supprimé

In a lump sum contract, the owner has essentially assigned all the risk to the contractor, who in turn can be expected to ask for a higher markup in order to take care of unforeseen contingencies. Beside the fixed lump sum price, other commitments are often made by the contractor in the form of submittals such as a specific schedule, the management reporting system or a quality control program. If the actual cost of the project is underestimated, the underestimated cost will reduce the contractor's profit by that amount. An overestimate has an opposite effect, but may reduce the chance of being a low bidder for the project.

 

target cost :- This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor's estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates.

 

In a unit price contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has been removed from the contractor. However, some contractors may submit an "unbalanced bid" when it discovers large discrepancies between its estimates and the owner's estimates of these quantities. Depending on the confidence of the contractor on its own estimates and its propensity on risk, a contractor can slightly raise the unit prices on the underestimated tasks while lowering the unit prices on other tasks. If the contractor is correct in its assessment, it can increase its profit substantially since the payment is made on the actual quantities of tasks; and if the reverse is true, it can lose on this basis. Furthermore, the owner may disqualify a contractor if the bid appears to be heavily unbalanced. To the extent that an underestimate or overestimate is caused by changes in the quantities of work, neither error will effect the contractor's profit beyond the markup in the unit prices.

Cost Plus Fixed Fee Contract  Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time.

 

 

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

I agree with comprehensive answer of Mr. Al Omar.

hatem labib
par hatem labib , Quality control manager , MISER consultant

the high risk for the contractor = low risk for owner = high price for owner =lumpsum project

the high risk for the owner = low risk of contractor= low price for owner =unit price project

 