How does the quantity surveyor manage construction costs?

user-image
Question ajoutée par dana tutunji , Architect , Helou Trading Co
Date de publication: 2013/08/01
dana tutunji
par dana tutunji , Architect , Helou Trading Co

Surveyors usually work to minimize the costs of a project and enhance value for money, while achieving the required standards and quality.

Abrar Hussain
par Abrar Hussain , Contract Manager , Sahara Tamiratt

The prime job of any QS is to Evaluate the Cost of work , provide guide line to the executing Engineers as per schedule of work planned and ensure implementation , keep todate data of demand and supply as per site requirements and manage it with the co ordination of procurement office with forecast of atleast fifteen days in advance. Keep the record of work executed and proceed for billing in time.

SAQIB ZAFAR
par SAQIB ZAFAR , Quantity Surveyor , PARSONS BRINCKERHOFF

Controlling variation from day one, with minimise risk and safety Saqib zafar Manager QS

MOHAMMED ABD EL HAY
par MOHAMMED ABD EL HAY , planning engineer , Khatib and Alami

At the start of studying the tender the QS have great part in the pricing procedure as for example the R.F concrete measured by the cubic meter in middle east but most of the B.O.Qs don’t include the steel ration in ....so it is necessary to calculate the steel ratio for every element ( footing, columns, beams, ceiling....etc ) which has a great effect on the unit price cost .

During the progress of the project the Q.S provide the quantities done till a certain point and what is remaining and from that we can determine if there is a waste in materials .

So the Q.S is deeply involved in the cost control.