With regard to the time element of controls, which of the following controls monitor activities while they are being carried out?

(a) Feedback (b) Feedforward (c) Precontrol (d) Concurrent (e) Preliminary.

user-image
Question ajoutée par Vinod Jetley , Assistant General Manager , State Bank of India
Date de publication: 2015/04/12
Sheila Marie Laurencio
par Sheila Marie Laurencio , Procurement Secretary , Reliance Electromechanical Plumbing and Contracting Co. LLC

d-concurent activity is the time element that is being carried out.

 

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Correct answer option D) <<<<<<<<<<<<<<<<<

     

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

(d)

With regard to the time element of controls, concurrent controls monitor activities while they are being carried out. Hence from above discussion, we can infer that option (d) is correct.

Utilisateur supprimé
par Utilisateur supprimé

The second answer

 

  (b) Feedforward

rohit mehra
par rohit mehra , Group GM - Finance and accounts , Sun and Sand Group

agree with Mr. Vinod Jetley's answer

Mohammed Shahid Ullah
par Mohammed Shahid Ullah , Executive Director (Finance) , Coal Power Generation Company Bangladesh Limited

Exactly, with regard to the time element of controls, concurrent controls monitor activities will be carried out.

 

Abbas Nasir
par Abbas Nasir , Project Coordinator , Huawei Technologies

Feedback is the control to monitor activity.

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

 (d) >>>>>>>>>>>>>>>>>> Concurrent

Almutaz Bakry Sidahmed
par Almutaz Bakry Sidahmed , Internal audit manager CIA & CCSA , Um Alqura Development

The answer is (d), concurrent controls while feedback controls are detective controls  after the occurance of an event, and feedforward are prevetive control before the occurance of an event.