1.A good construction sequence will allow for as many overlapping activities
as possible, without causing safety problems.2.Method statements allow for the most economical way of working to be
identified. They can be prose or tabular and can include health and safety
provisions that are required.3.Precedence diagrams are one of the best tools for preparing construction
programmes, as they allow for very complex relationships to be easily
incorporated.4.Regardless of how programmes are prepared, they are virtually always
presented as bar charts, and computer programs are used extensively to
prepare these programmes.
par
Osman Guni , STRUCTURAL ENGINEER , BUREAU VERITAS (BAN) PVT LTD
Sequence studies enable building programmes to be produced that are
effective as tools of control during construction works, and provide the most
efficient method of working.