Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Define the scope first (Requirements)
Create the WBS
Define Activities
sequance them
estimate activitiy resources
estimate activities duration
create the schedule
Ahmed Ghannam replied well, if someone needs more detail he/she can google it or visit
http://office.microsoft.com/en-001/access-help/control-data-entry-formats-with-input-masks-HA.aspx
1- Project total duration from the contract to compare it with the one you will plane
2-BOQ (Wich include Project Activity and quantity of work)
3-the logic in other word ,the knowing of relationship between activites
4-Resources (Labor Equipment material) and its production rate in order to calculate Activites duration 5-Resources unit price and the indirect cost in order to calculate Budget cost
Work Breakdown Structure, List of All Activities, Estimates, Network Diagram, Critical Path.
Reqd.WBS, DURATION OF THE SCHEDULE.
Three main things are generally requried to make a time schedule
1.Project Start date
2.Time duration for all activities
3.Relationship beteween activities.
when starting to entering the actvites you must enter the duration for each actvity and start date already you set anthor compnent cost, buddget, resours, work break down structure