What are the inputs required for making a time schedule?

user-image
Question ajoutée par Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date de publication: 2013/08/04
Khaled Alhassoun
par Khaled Alhassoun , Consulting Management - Senior manager , Price waterhouse Coopers

Define the scope first (Requirements)

Create the WBS

Define Activities

sequance them

estimate activitiy resources

estimate activities duration

create the schedule

 

 

Ahmad Ghannam
par Ahmad Ghannam , Zone Manager , Nokia


1- Tasks
2- execution time
3- which task depend to what before or after
4- Budget cost

Tanveer Ahmad Niazi
par Tanveer Ahmad Niazi , CEO (Self-employed) , Project Management Training & Consultant

Ahmed Ghannam replied well, if someone needs more detail he/she can google it or visit

http://office.microsoft.com/en-001/access-help/control-data-entry-formats-with-input-masks-HA.aspx

Anisuddin Siddiqui
par Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

Follow these steps: 1.
Learn the scope of works - Assign a Calendar 2.
Create a WBS to achieve this scope.
3.
Add activities in each WBS for which you need to know Activity Description in brief Activity Duration Resources required Sequence of operation or relationship with other activities Then work your way in Primavera, just press schedule and watch out for the project finish date.
 

Mohamed  Ali PhD Cand  MSc PMP PMISP
par Mohamed Ali PhD Cand MSc PMP PMISP , Project Control Manager , SEDER GROUP

1- Project total duration from the contract to compare it with the one you will plane

2-BOQ (Wich include Project Activity and quantity of work)

3-the logic in other word ,the knowing of relationship between activites

4-Resources (Labor Equipment material) and its production rate in order to calculate Activites duration 5-Resources unit price and the indirect cost  in order to calculate Budget cost

 

 

Ramendra Sunder Sinha PMP
par Ramendra Sunder Sinha PMP , DGM Planning , Gaur Sons Limited

Work Breakdown Structure, List of All Activities, Estimates, Network Diagram, Critical Path.

Kamran Umar
par Kamran Umar , PUBLIC RELATIONSHIP , CDGK

Reqd.WBS, DURATION OF THE SCHEDULE.

MOHAMED IMRAN
par MOHAMED IMRAN , Planning and Scheduling Engineer , ARABIAN GULF CONSTRUCTION

Three main things are generally requried to make a time schedule 

 

1.Project Start date

2.Time duration for all activities 

3.Relationship beteween activities.

mohmed osman salah eldin elshayib abbasher
par mohmed osman salah eldin elshayib abbasher , مدير تنفيذي , شركة سما حائل للمقاولات المعمارية

when starting to entering the  actvites you must enter the duration for each actvity and start date  already you set anthor compnent cost, buddget, resours,  work break down structure 