Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

When are update progress and apply actual get used in P6 schedule?

user-image
Question ajoutée par Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date de publication: 2013/08/04
Anisuddin Siddiqui
par Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

Once a Schedule has been completed, approved and a baseline set then you may start updating it based on the execution in case the project has already started.
The actuals are applied once details are collected from site.

More Questions Like This