A direct manufacturing labor overtime premium should be charged to a specific job when the overtime is caused by the:

a. Increased overall level of activity.

b. Customer’s requirement for early completion of job.

c. Management’s failure to include the job in the

production schedule.

d. Management’s requirement that the job be completed

before the annual factory vacation closure.

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2015/05/07
Saidul Alam
par Saidul Alam , Accountant , Akhtar Al Balushi Trad. & Cont. L.L.C

Answer b. Customer’s requirement for early completion of job.

Ednalyn Banuelos, CMA
par Ednalyn Banuelos, CMA , Projects Accountant , Grade Ref., LLC

Answer is B as per customer's requirement

Utilisateur supprimé
par Utilisateur supprimé

Answer B is the right option by customer 's requirement .