Accept the project if IRR is greater than the discount rate; reject the project if it is lower than the discount rate.

user-image
Question ajoutée par Shahbaz Hayder , Group Head of Finance , Sharif Group of Companies
Date de publication: 2015/06/03
Shahbaz Hayder
par Shahbaz Hayder , Group Head of Finance , Sharif Group of Companies

Yes True is the right answer.

Wasim khan wazir
par Wasim khan wazir , Finance Specialist , Mott Macdonald

Yeah its true. i would be worthwhile

Harish Rahim
par Harish Rahim , Assistant Vice President (AVP) , Credit Suisse

Yes True. Accept the Project if IRR is greater than the discount rate.

Shazia Anees
par Shazia Anees , Assistant Manager Finance , Arham Trading Company

true==============================