How do you calculate man-hour?

user-image
Question ajoutée par kabiru omotosho , hse coordinator , baklang group
Date de publication: 2015/06/24
Michael Owen
par Michael Owen , grounds maintenance , private

  1. Multiply the five-day work week by 12 weeks: 12 by 5 = 60. Subtract the two holidays for 58 days.
  2. Multiply the number of work days by 10 hours per day: 58 by 10 = 580 these are the project hours per employee.
  3. Multiply the per-employee man hours by the number of employees on the job: 580 by 5 = 2,900.