Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

How can we make a cost estimation(BOQ) for installation only for a fire alarm system for project?

user-image
Question ajoutée par Ahmed shawky , Team Leader Electrical Technical Office , Redcon Construction
Date de publication: 2015/06/28
osama ahmad
par osama ahmad , Technical Head - Building Services, ICT and Visual Systems , Al Rashid Trading and Contracting Company

Installation Cost = Material Delivery Cost from Client Warehouse to Site, Material storage cost at site, Cabling and Containment Cost, Termination Equipment Supply and Installation Cost, Site Access restrictions factors, Labor Cost, Accommodation Cost, Transport Cost, and the percentage of profit. 

All these cost will be calculated against time. Might have missed something 

More Questions Like This