When using the AGILE methodology, project tasks will be:?

a. Iterative and adaptive

b. Iterative and incremental

c. Incremental and adaptive

d. Predictive and adaptive

user-image
Question ajoutée par Liza Aidarashvili , Marketing Manager , NIT - an Ingram Micro Company
Date de publication: 2015/07/25
Liza Aidarashvili
par Liza Aidarashvili , Marketing Manager , NIT - an Ingram Micro Company

b. Iterative and incremental

The AGILE methodology is ITERATIVE and INCRIMENTAL, meaning that the project may go through repeated cycles and each cycle adds some sort of functionality, knowledge or value to the project. When using the AGILE methodology, the work on the next phase is being planned while working in the current phase.

Yaqoub Alomar
par Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality

Option - C -

-------------------

--------------------