Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
I guess I could substantially answer your question as I briefly summarized below;
1. As planned- is to prepare our implementation schedule based on tender schedule and original contract information reflecting detailed scope of works. This schedule will be our original baseline showing cost, time and other important resources.
2. As impact - is to prepare a revised schedule based on approved contract addition or subtraction and it will gauge its impact to the project as a whole in terms of cost, time and other vital resources. This schedule should be timely prepared and submitted for approval.
3. As built - is our actual monitoring of project phases such as engineering, procurement and construction comprising of cost, time and vital project resources. This schedule reflects our project completion in various areas/discipline and is an indispensable document during the project handover.
Best regards.
The procedure is to develop a plan and save it as a baseline time schedule and then assign it to the updated schedule so we can control the deviation comparing with baseline and take appropriate correction to mitiage this impaction
We will demonstrate this method by using a simple House project as below.
The House project has an As-Planned schedule like the following picture:
Project duration is 40 days.
The project finished and As-Built schedule is as below:
Actual project duration is 51 days.
This As-Built schedule already included all delay events which is documented in the below table:
Source: Construction Delay Analysis Technique – A Review of Application Issues and Improvement Needs – Nuhu BraimahType of Delay:
Create another As-Planned schedule which has a Start/Finish date look like As-Built schedule. This schedule is called “As-Built Calculation Schedule”
Separate delay events to a different project so that later we can exclude them.
Hi,
I write an article regarding How to perform Impacted As-Planned Delay Analysis in Primavera P6.
If you're interested, kindly read it here https://doduykhuong.com/2016/09/19/how-to-perform-impacted-as-planned-delay-analysis-in-primavera-p6/
1 Understand Contract and Specification Requirements It is important for the Planner/Scheduler to understand the contract and specification requirements for schedule updates. These documents should outline frequency of updates, procedures for updates versus revisions, earned value requirements, cost and/or resource status requirements, and change management procedures. These documents may also require specific software to be used.
2 Determine Update Frequency In order to effectively record and measure project progress consideration should be taken as to regularity of updates. Internal company policy, project budgeting constraints, and application usage are factors in establishing schedule update occurrence
1. As planned- is to prepare our implementation schedule based on tender schedule and original contract information reflecting detailed scope of works
2. As impact - is to prepare a revised schedule based on approved contract addition or subtraction and it will gauge its impact to the project as a whole in terms of cost, time and other vital resources.
As built - is our actual monitoring of project phases such as engineering, procurement and construction comprising of cost, time and vital project resources