WHAT IS THE PERCENT THAT MUST BE INCREASED TO THE DIRECT COST FOR RISK , DELAY AND INCREASE THE COST OF MATERIALS FOR ANY PROJECT IN THE ESTIMATION STAGE?
Question ajoutée par
Anwar Abdulhady
, MBA- PMP-MEP- Projects Director - Coordinator - Cost Estimator , Sertah United Company
Date de publication: 2015/09/01
THE PERCENT THAT MUST BE INCREASED TO THE DIRECT COST FOR RISK IS a ratio from the direct cost and it is estimated as a part of the risk assessment after completing the quantitative risk assessment so the ratio in between (0 :25% ) of the Direct Cost & for Normal projects it dos not exceed12% of the Direct Costs