Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In lump-sum projects if you found that your price in one item is very less than the actual cost of it, can you claim a variation?

user-image
Question ajoutée par Osama Setohy MCIOB , Senior Quantity Surveyor , Keo International Consultants - Qatar
Date de publication: 2015/09/27
Bahaa Al Khamees
par Bahaa Al Khamees , Senior Quantity Surveyor , Faithful+Gould Saudi Arabia Ltd.

unless you have a new quantity change, you cannot claim for unit rate change.

Vetri Selvan Manikkam
par Vetri Selvan Manikkam , Assistant Manager -Quantity Survey , Larsen & Toubro (Oman) LLC

Once you prices and the price accepted by the both the parties , you can not change the price. It is your duty to price the item correctly. We do not give the credit to the client once the atucal rate of particular item is lower than our price .

suresh Murugan
par suresh Murugan , Senior Quantity Surveyor , Havelock One Interior WLL

No you cannot claim as a variation order. Only possible to Amendment the contract.

Aslam Sujah
par Aslam Sujah , MEP Quantity Surveyor , Services & Trade Company LLC

You can't claim. And also the specific item's rate increased more than before. Then also you cannot apply for a variation.

 

If client request to change the item or adding more quantity of that item, then only you can apply for a variation. 

Hussein Ali
par Hussein Ali , Commercial Manager , Hill-EHAF JV

No you can not as this item was included within the contract documents when you signed it.

you can claim if it is a variation item.

Mohamed Kamal
par Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

no you can't you accepted to take all the risk for the contract and should have deeply reviewed this in your estimation phase.

Paul Lou dela Cruz
par Paul Lou dela Cruz , QUANTITY SURVEYOR , FIBREX CONSTRUCTION GROUP

No. You can not claim it as variation unless the client requested to change that item.

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

It is impossible to claim as the itemized price confirmed in the contract document and could not be changed till the customer asking for the some items change or adding some quantities then you can make a variation order with new items prices and quantities with new conditions for the deliveries. 

Tanveer Ahmed
par Tanveer Ahmed , Civil Estimator/Quantity Surveyor , Shade Corporation Ltd.

No. But if there is any price escalation of material then we can claim it.

Bharath Ebenezer
par Bharath Ebenezer , Jr.Quantity Surveyor , Archimedes India Associates

If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities originally contemplated are so changed in a proposed Change Order or Construction Change Directive that application of such unit prices to quantities of Work proposed will cause substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably adjusted.

FAYYAZ MALIK
par FAYYAZ MALIK

In my view you can by providing some add on free of cost and signing the addendum after negotiation. all those who are saying no. In my opinion are thinking introvert.

Go out talk to client dive him some extra and save more profit.

Those who are saying no are basically Degree holder they have very less experience practical business    

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?