Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which is duty of QA QC Engineer? 1.Prepare PQP. 2.Prepare Method Statement. 3.Check Site work. 4.Submit Inspection Request. 4. All the above.

user-image
Question ajoutée par Anjum Jamal , QA QC Engineer , Khatib & Alami
Date de publication: 2015/11/13
Mohamed Sayed Abd El-Aziz
par Mohamed Sayed Abd El-Aziz , Projects Manager , Rawabi Butec

Method statement preparation should be prepared by the concerned person who will execute the work. 

Iftikhar Choudhary
par Iftikhar Choudhary , QA/QC Supervisor , Al Ghurair aluminium Constration -arabia-KSA

QA/QC Review the Method Statement and conduction Inspection Site work and Submit IFR after completion and of Internal site inspection request by Project site team.

 

Mubashir Muhammed Alathumkandiyil
par Mubashir Muhammed Alathumkandiyil , TA Supervisor , Qatar Shell GTL

As a QC review method statement and give quality wise inputs to the person who prepares it. Inspect work at its progressing levels and give suggestions or stop work if anything is against quality standards. Do follow checklists of specific standard during inspection  and prepare punch-list if it is necessary. Finally prepare request for inspection from client side or if you are from client side check punch-list and add any punch points if it is necessary and check whether they are cleared before closing the item.

Baris Celik
par Baris Celik , project Quality Control Manager , Neom Green Hydrogen Company

1/2/3 and some other. But not number4. Construction needs to submit Inspection request. 

Sabith Elamana mohammed kunju
par Sabith Elamana mohammed kunju , Project QAQC Manager/ QMS Auditor , Sun engineering and contracting company

The method statement should be preapred by the Construction team (Execution team) and QAQC should review and prepare the Inspection test plan based on the Method statement and specs. Risk shall be assesssed by HSE team as per Method statement.

More Questions Like This