Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is the difference between planning and budgeting in SAP ?

user-image
Question ajoutée par Mohammed Mohammed , Senior SAP Consultant , Abyat Mega Store
Date de publication: 2016/01/19

SAP makes a distinction between planning and budgeting. Planning implies that an iterative process may occur in which many different versions of the plan may be developed until one is decided upon. The budget which can be defined as a detailed work plan describing how the approved amount will be allocated is developed once the overall plan has been confirmed.

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

Budget is an approved cost structure for an action or project in a particular period of time.

 

Budgeting differs from cost planning in that it is binding. While you must estimate costs as accurately as possible during the planning phase, it is in the approval phase that you prescribe your funds, in the form of a budget.

Sajid Bashir
par Sajid Bashir , Assistant Manager Supply Chain , Hayat Kimya Pakistan (Pvt) Ltd

Budgeting is meant for monitoring the utilization of funds, either monthly bases or yearly.

Planing is meant for spending budget funds, either daily bases or monthly. 

 

Gopinath Sriperumbuduri
par Gopinath Sriperumbuduri , Senior Consultant - SAP FICO , G4S India Limited

Planning is financial estimate to prepare the organization for the future possible situations that it is likely to face in the environment in which it operates.

 

Budgeting is a control process to ensure that actual expenses do not exceed the assigned limit for a type of expense.

Utilisateur supprimé
par Utilisateur supprimé

SAP Planning - outlines the company's financial direction and expectations for the next three to five years.

     SAP Budgeting - documents how the overall plan will be executed month to month,   

     specifying expenditures.

 

 

Dexter James Smith Primero
par Dexter James Smith Primero , Division Secretary to Saudi Aramco (Supply Manpower) , Al-Falak Electronic Equipment & Supplies Co.

Both are different. 

Budgeting is to utilize and monitor the funds for a certain period but Planning is different as the values may diffeer from the budgeted values.

 

 

haq shaik
par haq shaik , Sap Solution Architect , Accenture - India

Budget is foretasted value decided  using  previous variance analysis for the current year.

But Planning should be in place again for the whole year and month on month to spend the  actually so that there will not be much  variance in the current year spend.

 

This is in regards to finance terms

sivannarayana appala
par sivannarayana appala , Project Lead , Larsen and Toubro Infotech Ltd

Budgeting is meant to monitor expenditure within approved limits and need controls, approvals for spending. 

Planning is meant for in-advance preparation for allocation of funds and to compare with actual funds utilization

Sanjiv Malhotra
par Sanjiv Malhotra , Operations Director and Head of Development and Resources , British Council

Budgeting is used to put an anuual financial cap and the spend cannot go above that figure. While planning is used to monitor actuals against each Cost elements, WBS, cost centre etc

Mahmoud Habeeb
par Mahmoud Habeeb , Package Solution Consultant S/4HANA Finance , IBM - Egypt

Planning is from down to top 

(Define the activities and collect the requirements to make the budget)

Budgeting is from top to down

(After planning you start execution within the budget)

 

Planning is input for budgeting 

Hammad Hassan
par Hammad Hassan , Store Officer , Attock Cement Pakistan Ltd

Theoretically, planning is related to strategies and long term management of your resources to achieve your business goals while budgeting is meant for managing and monitoring how you spend your funds in your day-to-day transactions.However, in SAP there are some differences between budgeting and planning that you should be aware of and we can put them under three main headings:

Level of details: When you record your planning in SAP, you are able to detail your planning as much as you can. You can plan by cost element, activity type, resource, etc. You can also plan using quantities and capacities. On the other side, budgeting uses one lump sum amount per object.

Availability control: Availability control is the function you use to make the system checks the available amount to be spent on a specific object and issue warning or error messages at some levels of spending. Availability control can be activated using budgeting and can’t be activated for planning. This means that you are just able to report on the variances occurred between planning and actual expenditures, but you cannot automatically stop spending over the planned amounts which is possible only using budgeting.

Allowed controlling objects: Planning can be done on all types of controlling objects, so you can plan on cost centers, profit centers, internal orders, WBS elements while budgeting is applicable only on the temporary or the project-like CO objects (internal orders and WBS elements). Actually, you can record a budget for a cost center but you can’t use availability control with it which is the main purpose of budgeting.

More Questions Like This