Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How to make an E.O.T for a Baseline when you are on the middle of the project and you do not have a monthly update before?

user-image
Question added by Osama El Sherif , Planing Manager , Al-Rashid Trading and Contracting Co.
Date Posted: 2016/02/23
Mamoun Salama
by Mamoun Salama

if you have approved baseline schedule, use the impacted as planned schedule analysis method because you have not an interval update 

Tarig Hussein Eltayeb Hamid
by Tarig Hussein Eltayeb Hamid , Resident Engineer , Tebodin Bilfiger middle east

in addition to the above mentioned, you can use the breakdown of affected activities (duration of activity) and apply it on days of delay. other way as cost wise as per BOQ

Omar Abdelmaksoud
by Omar Abdelmaksoud , Senior Contract Administrator , Orascom Construction

I agree with Mr. Maamoun, the solution is to use impacted as planned technique, you won't need schedule update.

More Questions Like This