Thanks for invitation..
to explain the different.. please look at this example:
Question:
What is the difference between connected load kva
and demand load kva on 277/4803 phase panel 400
amp?
Answer:
Connected Load is the total load you have connected to the 400 amp panel.
As you probably know, all of that load is not on at
same time. The max demand load is the maximum load
that is on during a predetermined period of time. If you live in a hot summer time region, the the peak load.
may be from
9am to 8pm when the A/C is running all of the time.