Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which Manufacturing Execution business process step has not been completed? (1 correct answer)

 Your organization uses SAP ERP Manufacturing Execution. You are reviewing a production order and notice that no labor time has been recorded in the production order.

A. Order settlement

B. Variance calculation

C. Goods issue

D. Confirmation

E. Goods receipt

user-image
Question ajoutée par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
Date de publication: 2016/04/03
Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Yes, only after confirmation of production order, labour time will be recorded

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Confirmation...........................

................................

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

D. Confirmation>>>>>>>>>>>>>>>>>>>>>>>>>>

More Questions Like This