Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In addition to balancing a line for a given cycle time, managers must consider what other options?

A) Pacing , behavioral factors, number of models produced and cycle times.

B) Line balancing, pacing, design flow, and cycle time

C) Mixed-model line, single modal line, idle time, and efficiency

D) None of the above

user-image
Question ajoutée par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
Date de publication: 2016/04/03
Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Mixed-model line, single modal line, idle time, and efficiency"""""""""""""""""""""""""""""

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Option A should be the appropriate answer because in balancing we need to consider pacing, no. of models produced, behavioural factors and cycle time

Vinod Jetley
par Vinod Jetley , Assistant General Manager , State Bank of India

C) Mixed-model line, single modal line, idle time, and efficiency

More Questions Like This