Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. It determines the planning period for the planning run
B. It determines the period in which the planned orders are to be converted into production orders
C. It determines the period in which no automatic changes are to be made to the production plan
Planning time fence don't allow any automatic changes (Ex.MRP execution) for the production plan on the determined period
Option C, Not automatic changes in the production plan in the specified period is the appropriate answer
Option B) is answer <<<<<<<<<<<<<<<<<<<<<<
B : IS THE CORRECT ANSWER FOR THE ABOVE QUESTION.
B. It determines the period in which the planned orders are to be converted into production orders