Material source to be used for building back filling having high chloride content. What shall be remedial action if no choice to use?

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/04/19
Joel Taer
par Joel Taer , Project Manager Consultant , Riyan Private Limited

The substructure exposed to the filling material shall be protected with some type of chemical treatment as barrier against incoming moisture and/or waterproof protective boards/sealant or tapes in order to protect the rebar and restoring concrete durability

Utilisateur supprimé
par Utilisateur supprimé

Since Chloride content will be high and react invariably to the conditions present, you must determine treatment strength outcome based on this. Rebar with proper irrigatiion must be present in order to reinforce the structure. 

Mohamed Youness
par Mohamed Youness , Client Representative , AJIP BV (ITALIAN) Libyan

All concrete contct surfaces with back filling material having haigh chloride content must have the following:

  1. Chathdic protection to protect reiforcemet st. rebars against corrossion (Piles and deep/shallow foundations and concrete/non concrete walls).
  2. Using water proofing insulation for sides surfaces and bottom side of foundation).