Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. duration
B. total flat
C. free float
D. interfering float.
free float is the correct answer...........
B : is the right answer - Total float : is the amount of time that an activity can be delayed without delaying the project completion date , because C : Free float : is the amount of time that an activity can be delayed without delaying the Early Start of its successor activity
Free Float Option " C " .
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?
3. free float
It shows option "C" is suitable one.
Free float...is the answer
.................. c . free float
C. free float
*****************
thanks for invition ,,,,,,,,,,
my choice is option C