Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Can Any Body explain the algorithm of Critical Path Method (CPM) use in Construction management?

user-image
Question ajoutée par Asim Ali Khalid , Project Engineer , AHN Construction
Date de publication: 2016/04/26
Ahmed Badawi
par Ahmed Badawi , Civil Site Engineer , Zaid Company for Building and Construction

  1. A list of all activities required to complete the project (typically categorized within a work breakdown structure) ,
  2. The time (duration) that each activity will take to complete,
  3. The dependencies between the activities and,
  4. Logical end points such as milestones or deliverable items.

DOMINGO BALABA
par DOMINGO BALABA , DESIGN MANAGER , MEPF) J AND E CONTRACTING & TRADING

FLOAT ACTIVITIES in Construction schedule where management considered a float activity which can be started earlier or at the end of the Construction period.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?