For completion of a project, the critical path of the network represents_.

A.     minimum time

B.     maximum time

C.     maximum cost

D.     minimum cost.

user-image
Question ajoutée par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date de publication: 2016/04/27
ghazi Almahadeen
par ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks for the invite ......................... D. minimum cost.A. minimum time...

emad namdar
par emad namdar , deputy of general director , Iraqi atomic energy commission- ministry of military manufacturing

Critical path represent minimum time of execution the project

Mahmoud Zaher Tarakji
par Mahmoud Zaher Tarakji , مدير , أوال جاليري

............A AND ....D...............

Yahia mohamed  Amen Gad
par Yahia mohamed Amen Gad , إدارة - مدرب - , سنابل الأجيال للتعليم والتدريب

Thank you for your call / a

Omar Saad Ibrahem Alhamadani
par Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

It is A & D................

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

The Answer is ...A. minimum time

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer is option D) <<<<<<<<<<<<<<<<<<<

ASIF BE Mech IEng PMP
par ASIF BE Mech IEng PMP , Projects Manager - Buildings Utilities & infrastructure , Qatar General Electricity & Water Corporation

In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project

Mohammed Abdelseed
par Mohammed Abdelseed , Maintenance Operations and Technical Support Section Head , Bashayer Pipeline Company

the Answer is "B", Critical Path is the longest path in the project net work, it will be calculated based on 'AOA", AON" -Critical Path method.

Abdullah Altuwayjiri
par Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

B.     maximum time

to be more accurate, it is the path that if any of its task get delayed by a specific time, the whole project will be delayed by the same amount of time

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

"A" minimum time,

thanks....