Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Why corrective action is performed in Project Management Plan?

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2016/05/10
sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

I am not sure if I got the question,

corrective action is applied when a failure or mistake happen so in order to eliminating root causes it might be necessary to perform some changes in project management plan.

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, i agree with experts answers

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Any action needed to bring future project performance in line with the project management plan is

called a corrective action. The three basic steps of Corrective Action:

• Identify the need to take corrective action

• Take corrective action

• Measure the result to determine if additional action is necessary

Corrective actions, preventive actions, and defect repair are recurring themes throughout the PMBOK®

Guide, 5th edition.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?