A.
1. Pouring of Concrete
2. Erection of form work
3. Curing of concrete
4. Removal of form work
B.
1. Erection of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work
C.
1. Removal of form work
2. Erection of form work
3. Pouring of concrete
4. Curing of concrete
D.
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work
In my knowledge. The correct answer is, B.
The correct sequence is : B
...........OPTION B ............
This is not my specialty................Thanks.
Erection of form work ,Pouring concrete,curing of concrete,Removal of formwork
-----------------------------------B-------------------------------------
sure the answer is option B
B is the only one correct sequence.
THE ANSWER IS B.BUT I DIDN,T UNDERSTAND WHAT IS THE SIGNIFICANCE OF THIS QUESTION