Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

How can this be best described in project management terms as? See below for details and options.

You have just collected project information from stakeholders and are analyzing their input with the project team. One stakeholder is worried about whether the organization has the proper skill sets in house to deliver the product of the project. 

a. A constraint

b. A potential risk

c. An issue

d. A and C

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/11
DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Option b is absolutely right answer.

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

option B,,,,,,,,,,,,,,,,,,

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D – This is not exactly a trick question, but it's close. The scenario described is not only a constraint (no

internal headcount with the skill set), but it is also an issue (if I need additional headcount, how do I go

about obtaining it?)

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

I think B is the answer,..

Thanks for invite

More Questions Like This