an adjustment to the PM plan. What should you do next as the project manager?
a. Implement a formal CR
b. Make the adjustment
c. Consult the change control board
d. Inform the stakeholder that this constitutes scope creep and refuse to make the change
B – Prior to baseline, the PM plan can be adjusted without a CR, consulting the change control board, or addressing a scope creep issue.
PMBOK® Guide, 5th edition p. 82.