The project management plan is complete and is ready to be baselined. However, a key stakeholder just discovered a critical omission and requests?

an adjustment to the PM plan. What should you do next as the project manager?

a. Implement a formal CR

b. Make the adjustment

c. Consult the change control board

d. Inform the stakeholder that this constitutes scope creep and refuse to make the change

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – Prior to baseline, the PM plan can be adjusted without a CR, consulting the change control board, or addressing a scope creep issue.

 

PMBOK® Guide, 5th edition p. 82.