Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following activities do you think involve Estimate Activity Resources?

  • You develop a resource breakdown structure (RBS)
  • Inquire of subject matter experts what resources will be needed
  • Determine resource availability for the project
  • Decompose activities into smaller parts to derive resource estimates.
  •  Analyze the WBS and the activity list
  • Perform an analysis of technical difficulty to build and deliver a project component
  • Perform an analysis of the type of resources needed for the project
  • Consult with HR on organizational resource use policies

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/14
Karen Ann  Smith
par Karen Ann Smith , Executive Secretary , Al Tamimi

Estimate Activity Resources is the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.

Reynaldo De Leon
par Reynaldo De Leon , I.T. TECHNICAL SUPPORT OFFICER , FUJITA CORPORATION, METRO RAIL PROJECT

develop a resource breakdown structure.

determine resource availability for the Project.

 

More Questions Like This